363 infrastructure projects show cost overrun of over Rs 3.42 lakh crore
For 700 projects, neither the year of commissioning nor the tentative gestation period has been reported. Out of the 375 delayed projects, 111 have overall delay in the range of 1 to 12 months, 61 are delayed by 13 to 24 months, 95 reflect delay of 25 to 60 months and 108 projects show 61 months and above delay.
Ministry of Statistics and Programme Implementation monitors infrastructure projects, Image source: PTI